Posted on: October 18, 2017

Construction Update for the Week of Oct. 23

The curb and walk “punch list” is set to be tackled Monday, Oct. 23 through Friday, Oct. 27. So, if you see any gaps in the new sidewalks or curb and gutter, they should vanish next week.

Once all of the sidewalk work is completed, resi...

Read on...

James Street Reconstruction Project
Posted on: October 11, 2017

Construction Update for the Week of Oct. 16

Pouring asphalt on West James Street approaches and intersections occurred today, Wednesday, Oct. 11, with all the incomplete approaches to be finished Thursday and Friday of next week. This should allow for easier access along the entire route for local ...

Read on...

James Street Reconstruction Project
Posted on: October 4, 2017

Construction Update for the Week of October 9th

The past month has been rather dry and as a result a number of residents have contacted City Hall concerned about their new sod. Contractors and State DOT are aware of the issue and are committed to keeping the grass alive.

The contractors will replace any...

Read on...

James Street Reconstruction Project
Posted on: September 27, 2017

Construction Update for the Week of October 2nd

For everyone wondering about the large dirt patches along the mostly finished stretches of road, fear not, the sod subcontractor will return to fill that brown with green. The areas torn up by the construction will be returned to a state better than they ...

Read on...

James Street Reconstruction Project