2022 Fuller Street Culvert Replacement

Beginning Monday, September 12, 2022, Fuller Street will be closed to motorists in order to replace the culvert. This project will have impact upon pedestrian traffic as well as motor vehicle traffic on Fuller Street and in the area. This work will especially effect parent/guardian drop off and pick up of students that use Fuller Street. Pending favorable weather and construction conditions, the project is estimated to be completed on Friday, October 21, 2022.

Fuller Street Culvert Replacement Site Traffic Map Download Link

During the project, Fuller Street will be completely closed to motorists and pedestrian traffic in order for the contractor to lay the new pipe. Motorists and pedestrians are asked to follow the posted detour. Vehicle and bus traffic should not detour using School Street as the narrow width of that street would make it unsafe.

In addressing potential safety concerns, there will be temporary no parking in the following areas:

  • Fuller Street from S. Dickason Boulevard to Ludington St (Park Avenue).
  • S. Dickason Boulevard. from Fuller Street. going north, mid-block to Richmond Street.
  • School Street from Ludington Street (Park Avenue) to S. Dickason Boulevard (both sides) from 7:00 AM to 4:30 PM Monday through Friday.

The contractor will reopen Fuller Street as soon as pipe is installed across Fuller Street, however the area will remain no parking until project is complete.

Fuller Street Culvert Replacement Timeline, From September 12 through October 21, 2022

Beginning Monday, September 12, 2022 replacement of the culvert at Fuller Street will begin. This will involve clearing and grubbing, erosion control, traffic control and mobilization.

9-13-22 through 10-1-22 sees substantial completion of the project with installation of 91" x 58" HERCP to replace the existing culvert.

10-2-22 through 10-14-22 involves restoration and closeout to finish construction.

Punch list items will be addressed from 10-15-22 through 10-20-22 with the project estimated to be completed on Friday, October 21, 2022 pending favorable construction and weather conditions.